2014年7月18日星期五

Raymond installation

1, first gear hanging into the pit filled base, pay attention to control a certain height, and then use the upper level meter calibration plane "A", while the transmission mounted "A" surface of the bolted.
2, Raymond host installation. Before installing rubber shock pad should pad the lower plane of the base and the cement foundation and anchor bolts connection between the contact points,Winnowing pulverizer Mill and then use the box-shaped instrument calibration base level "B" plane, the calibration point for the cross crosshair four points, while linking the two halves of alignment axis is "C", "D", which should be less than misalignment 0.20 mm, E1 - E2 shall not be greater than 0.1 mm parallelism, "E1", "E2" the gap should be kept within 5-8 mm.
3, the location and height of the pipe means the total figure should be installed,Raymond Millone shall be arbitrarily altered and heightening the pipe joints should be sealed, without leaks after tightening. Electrical equipment should be accurate and reliable, the test machine should be installed upon the components

没有评论:

发表评论