Raymond debug (empty running test machine)

An empty load test machine running at no load test machine before grinding roller device should hold the roll firmly with rope nets to avoid contact with the impact of the roller and grinding ring, and then empty the host machine running the test less than one hour; Host should operate smoothly, cabinets oil should not exceed 80 ℃,TengFei Raymond Mill temperature does not exceed 40 ℃.
2, the blower should load the boot, to be operating normally after the load, and then observe its smooth operation, no abnormal noise and vibration, bearing the maximum temperature should not exceed 70 ℃,Winnowing pulverizer Mill the temperature rise should not exceed 35 ℃.
3, the load test machine running time of less than 8 hours after the machine is working properly Raymond no abnormal noise, the pipe joints leak wind phenomenon, the test machine again after each fastener tightening, can be put into normal use.